Petoskey, MI
Petoskey, MI

Marina Parking Lot Resurfacing

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$150,000

Overview

DepartmentPARKS AND SPECIAL FACILITIES
Project NumberPSF-2805
CategoryParks and Recreation

Project Description

The parking lot will be 38 years of age and will be in need of resurfacing.  The lot has been used to house marina spoils prior to disposal which accelerated the decline of the top coat.  In 2010, the lot was patched to accommodate the marina expansion utilities.  Grant and restricted marina funds will be used to finance the lot resurfacing.

Spend

Expenditures2028Total
Project Cost150,000150,000
Total150,000150,000
Funding Sources2028Total
General150,000150,000
Total150,000150,000