Petoskey, MI
Petoskey, MI

Marina Pier B Upgrades

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$300,000

Overview

DepartmentPARKS AND SPECIAL FACILITIES
Project NumberPSF-2604
CategoryParks and Recreation

Project Description

The electric system in Pier B needs to be updated to match the rest of the docks.  Currently there are only three breakers for 54 slips and power outages are increasingly common.  In addition, new deck boards should be installed as part of the project.

Project Justification

This is referenced in the 2023-2027 Parks and Recreation Master Plan.

Spend

Expenditures2026Total
No Name0
Project Cost300,000300,000
Total300,000300,000
Funding Sources2026Total
General150,000150,000
Grants150,000150,000
Total300,000300,000