Petoskey, MI
Petoskey, MI

Pavement Preservation - Standish Avenue

Powered by PlanIt!

Capital Cost

TOTAL PROJECT COST$745,000

Overview

DepartmentSTREETS AND DRAINAGE
Project NumberS&D-2702
CategoryPublic Works

Project Description

The purpose of this project is to repair or rehabilitate existing pavement and curb lines. The Little Traverse Bay Band of Odawa Indians (LTBB) will be providing grant monies through the Federal Bureau of Indian Affairs (BIA) to rehabilitate Standish Avenue from Buckley Avenue to City limits along with the addition of new sidewalk (east side).

Spend

Expenditures2027Total
Project Cost745,000745,000
Total745,000745,000
Funding Sources2027Total
Grants745,000745,000
Total745,000745,000