Capital Cost
TOTAL PROJECT COST$699,000
Overview
DepartmentELECTRIC SYSTEM
Project NumberES-2803
CategoryPublic Works
Project Description
Conversion of the 46kV transmission line and circuits PET6 and PET8 to underground from Petoskey Substation to the south side of the salt shed. Improves reliability of the transmission service into the substation, prepares for voltage conversion of circuit PET8, and creates required space for expansion of the DPW building.
Spend
| Expenditures | 2028 | Total | ||
|---|---|---|---|---|
| Project Cost | 699,000 | 699,000 | ||
| Total | 699,000 | 699,000 | 
| Funding Sources | 2028 | Total | ||
|---|---|---|---|---|
| Electric | 699,000 | 699,000 | ||
| Total | 699,000 | 699,000 | 